Davidson Education Building

UPDATE - Aug 28.  All remediation and restoration work is complete.  Room 303 waiting on new wall to wall carpet to be selected and installed.  Area rugs for 304, 305 and 306 are being selected and purchased.

UPDATE - Aug 31.  All remediation and restoration will be completed by end of dayAug 31.  Furniture should be placed back in appropriate rooms by end of day Sep 4.  Rms 303, 305 and 306 require new carpet.  Once carpet choices are comfirmed by Kelli and Dana, order will be placed and expected delivery date will be communicated.  Rms 305 & 306 are fully functional without new carpet, Rm 303 is not functional until new carpet is installed.

Aug 13, 2018.  Due to significant rainfall in a short amount of time, the city of Wayne experienced flash floods and general stormwater managment issues.  Water damaged the 3rd floor and portions of the 2nd and 1st floor of the Davidson building.  Remediation and Restoration projects began immediately.  Current estimate is have all restoration projects complete by Aug 31 end of day.  Upon completion, all areas of the building that were affected will be dry, treated with a plant-based microb inhibitor, replastered and repainted as needed.  Room 303 wall to wall carpet will be removed and replaced.  Other area carpets on the 3rd floor that were affected will be removed and replaced.  

Any questions relating to this work, please contact the Property Committee or Neil Hartman.

Play Deck

August 13 2018 -  Due to the Wayne PA area significant rain and resulting city-wide flooding,  the church experienced water intrusion issues.  The play deck roof along with the main roof of the Davidson Education building, while not showing obvious issues, are being inspected to determine how water entered both the Davidson building and Rm 209 (under the play deck).

June 6, 2018 - The ceiling in Rm 208/209 is directly under the Play Deck.  Over the years, this Play Deck roofing system has experienced a variety of issues, mostly resulting in water penetration to the ceiling in Rm 208/209.  This summer, we are taking another attempt to understand the root cause of the water penetration to Rm 208/209.  The current thinking is that during heavy, prolonged rains (or large amounts of snow), the water on the Play Deck cannot drain fast enough and therefore, the water level rises to above the flashing on the roof.  This allows water to penetrate the building and find its way to the ceiling in Rm 208/209.  We will be investigating this theory during the summer months.  Based on what we learn, appropriate modifications to the roofing system will be made.

 

Davidson Bldg, 1st Floor Men's room

UPDATE - Aug 27, 2018.   All ceiling repairs and paint have been completed.  

The ceiling in this men's room experienced water damage from the 3rd floor men's room toilet.  The toilet is being replaced.  The ceiling is being repaired.  Estimated completion is by end of June 2018.  Repainting of the ceiling will be coordinated with other paint projects in order to save $.

 

 

Rm 303

Jan 19 - UPDATE.  Painting has been completed.  Room is back in service.

Jan 15, 2018 - Room 303, Davidson Hall education building, is being completely repainted.  Estimated completion date, end of day Jan 18.  Please see Wendy Devlin for temporary scheduling changes due to this room being unavailble during this project.

Kitchen

Jan 12 UPDATE - The kitchen is back to being fully operational.  Gas line issue has been corrected.

Jan 2, 2018 - The kitchen oven and stove are currently not working due to a detected leak in a gas line supplying the kitchen.  This gas line has been turned off to the kitchen until repairs have been completed.  Current estimate for completion is Jan 12.  

North Connector Doors

Jan 22 UPDATE - Work has been completed.  Doors are fully operational.

Jan 5, 2018 - The North Connector doors from the main parking lots are not working due to weather conditions.  The ground outside of these doors has frozen and heaved to the point where the doors will not open.  We are working on options to correct.